OFFICE MODULAR 2 (OM2) BUILDING
This project proposes a new temporary modular structure, that will closely mirror Office Modular 1 (OM1) in size, function and appearance, to address immediate space needs resulting from growth in UBC Okanagan’s academic programs. OM2 will be a 536 m2 building that will include a washroom facility to serve both OM1 and OM2.
Existing OM1 Building (Right) adjacent to OM2 site (Left)
Development Approval Application
DA2022-01
Location
North of OM1 (east of Transit Exchange and south of University Way, UBC Okanagan)
Proponents
UBC Okanagan Project Services
Public Comment
Not Applicable for Minor Capital Projects
Contact
Hailey Rilkoff
Project Planner, Campus Planning
(250) 317-6586
Attachments
None
Timeline
March 21, 2022 – Development Approval materials received
April 5, 2022 – Development Approval DA2022-01 Issued
Fall 2022 through Summer 2023 – Construction